New Delhi: The strength ministry has planned to develop an extra ninety seven GW coal and lignite-primarily based power era ability to obtain the required 307 GW of thermal set up ability by means of 2034-35, parliament become informed on Thursday.


This assumes importance in view of India’s ambitious target of 500 GW of renewable energy capacity with the aid of 2030 and net 0 goal by 2070.


In a written reply to Lok Sabha, minister of nation for power Shripad Yesso Naik said, “The projected thermal (coal and lignite) ability requirement by way of the 12 months 2034-35 is predicted at about three,07,000 MW as towards the two,eleven,855 MW set up capability as on march 31, 2023.” The minister informed the residence that to satisfy this requirement, the Ministry of energy has envisaged putting in an additional minimum of ninety seven,000 MW of coal and lignite-primarily based thermal capacity.


The established electricity technology capability within the united states is 485 GW as on june 2025. As in keeping with the national strength Plan (era) posted in may also 2023, India's hooked up era potential is possibly to boom to about 870 GW through 2031-32. Thermal capacities of round 11,680 MW have already been commissioned seeing that april 2023 till june 2025.


similarly, 38,935 MW (which include five,695 MW of burdened thermal power tasks) of thermal capacity is presently below construction, the minister said. Contracts for 15,440 MW thermal ability were awarded in FY 2024-25 and are due for creation. to meet the projected call for within the u . s ., 35,460 MW of coal and lignite-primarily based candidate potential has been diagnosed, that's at diverse ranges of making plans within the united states, it stated. He also informed the house that thirteen,463.5 MW of Hydro electric tasks are below creation.


further, 9,802 MW of Hydro electric tasks are below various levels of making plans and centered to be completed via 2031-32. As an awful lot as 1,58,450 MW Renewable potential, which includes seventy four,a hundred and fifty MW of solar, 30,080 MW of wind and 53,750 MW hybrid power, is under production at the same time as sixty two,000 MW of renewable capability, such as 46,010 MW of solar and 15,990 MW hybrid power, is at numerous stages of making plans and focused to be completed by way of 2029-30, he said.


In energy storage systems, eight,250 MW/49,500 MWh Pumped garage tasks (PSPs) are beneath production, he said. a complete of 5,780 MW/34,680 MWh capability of PSPs are concurred and but to be taken up for construction. of these, three,500 MW/21,000 MWh ability of PSPs are below bidding, and 15,829 MW/fifty one,106 MWh Battery electricity garage system (BESS) are currently underneath various degrees of production/ bidding, he additionally said.


Nuclear potential of 6,600 MW is underneath construction and focused to be completed through 2029-30, the minister stated, adding that approximately 7,000 MW of nuclear capacity is under diverse levels of making plans and approval. there was an increase in energy demand within the us of a because of numerous elements, like rapid financial increase, accelerated family electrification, growing urbanisation, growing residing standards and the developing use of electricity-extensive technology, which include air conditioners and electric vehicles, the minister stated.


As in line with the mid-time period overview of the 20th electric powered energy survey (EPS), the electricity call for due to electric powered vehicle (EV) charging is anticipated to be 63,651 MU (approximately 2.35 according to cent of projected general call for) by means of FY 2031-32. good enough generation potential has been deliberate to fulfill the growing call for of energy inside the u . s ., along with due to the rise in EVs, he stated.